We've made some great progress on this project over the past few weeks.

New asphalt has been put down for the new accessible (DDA) car spaces and car park entry. We've also installed new pathways to the pool entry to provide better access for everyone.

Inside the pool amenities building, structural works and services are 90% finished. Our contractor is now working on tiling and other interior finishes.

We've removed the old tile from the pool, and concrete repairs are underway on the pool shell to extend its life.

We've also finalised the design for the plant room and ordered new filtration equipment that will keep the pool working better during the busy summer season.