We've continued to make good progress on all parts of this project.
Structural remediation works on the pool shell are finished, and all of the protective anodes have been installed and tested. The pool hobs have been re-rendered square and are ready for tiling.
The concourse has also been resurfaced.

Inside the amenities block, most of the fitout is done. New joinery, basins and toilets have been installed.


Outside, landscaping has continued with some new furniture, bubblers and sandstone seating recently installed.
We're nearing the end of this project, and the team will keep pushing ahead through the Christmas period.
We're hoping to confirm a reopening date at our next update in January.