After some supply-related delays last month, works have pushed ahead and we've made some great progress on works at Helensburgh Pool.
Both the main pool and toddlers' pool are looking good, with the tiling and grouting recently finished. We need to give the glue and grout a little more time to cure, then we can get to the exciting part - filling them up!


In the plant room, the new filtration system is almost completed and will be ready for dosing and filtering the new water shortly.

Outside the pool entry, linemarking for the new DDA parking spaces has been finished. We've also installed new paving, fresh turf and finished the new concourse at the entry.