Contracts Register - Class 3
| Contract NumberContract Number | Contract NumberN1000017 |
|---|---|
| Contract DescriptionContract Description | Contract DescriptionWWARRP Stage 2B-2 Cell - Selective tender flowing on from EOI process A1000009 |
| ContractorContractor | ContractorDECC Pty Ltd |
| Address of ContractorAddress of Contractor | Address of ContractorUnit 30/19 McCauley Street |
| Contractor SuburbContractor Suburb | Contractor SuburbPORT BOTANY |
| Contractor StateContractor State | Contractor StateNSW |
| Contractor PostcodeContractor Postcode | Contractor Postcode2036 |
| Related CompaniesRelated Companies | Related CompaniesNot Applicable |
| Start DateStart Date | Start Date29-Nov-2023 |
| End DateEnd Date | End Date16-Jun-2026 |
| Estimated contract amount (incl. GST)Estimated contract amount (incl. GST) | Estimated contract amount (incl. GST)$22,157,283.98 |
| Description of provision where amount can be variedDescription of provision where amount can be varied | Description of provision where amount can be variedAs per contract |
| Provisions for RenegotiationProvisions for Renegotiation | Provisions for RenegotiationNot Applicable |
| Method of TenderingMethod of Tendering | Method of TenderingNegotiated Contract |
| Provision for Operational or Maintenance ServicesProvision for Operational or Maintenance Services | Provision for Operational or Maintenance ServicesNot Applicable |
| Particulars of Future Transfer of Significant Assets to the State at Zero CostParticulars of Future Transfer of Significant Assets to the State at Zero Cost | Particulars of Future Transfer of Significant Assets to the State at Zero CostNot Applicable |
| Particulars of Future Transfer of Significant Assets to the Contractor including proposed transfer dateParticulars of Future Transfer of Significant Assets to the Contractor including proposed transfer date | Particulars of Future Transfer of Significant Assets to the Contractor including proposed transfer dateNot Applicable |
| Results of Any Cost Benefit AnalysisResults of Any Cost Benefit Analysis | Results of Any Cost Benefit AnalysisNot Applicable |
| A Summary of Information Used in the Full Base Case Financial ModelA Summary of Information Used in the Full Base Case Financial Model | A Summary of Information Used in the Full Base Case Financial Model |
| Particulars of How Risk Will Be Apportioned Between Parties if RelevantParticulars of How Risk Will Be Apportioned Between Parties if Relevant | Particulars of How Risk Will Be Apportioned Between Parties if RelevantAs per contract |
| Component and Quantum of Public Sector Comparator if usedComponent and Quantum of Public Sector Comparator if used | Component and Quantum of Public Sector Comparator if used |
| Particulars of Any Significant Guarantees or Undertakings Between the PartiesParticulars of Any Significant Guarantees or Undertakings Between the Parties | Particulars of Any Significant Guarantees or Undertakings Between the PartiesAs per contract |
| Particulars of Project / Goods / Services Provided, or Real Property to be Leased or Transferred Under ContractParticulars of Project / Goods / Services Provided, or Real Property to be Leased or Transferred Under Contract | Particulars of Project / Goods / Services Provided, or Real Property to be Leased or Transferred Under ContractProject PJ-4219 |
| Any Other Key Elements of the ContractAny Other Key Elements of the Contract | Any Other Key Elements of the Contract |
| Evaluation CriteriaEvaluation Criteria | Evaluation CriteriaCost to Council |
| Evaluation CriteriaMethodology | |
| Evaluation CriteriaPrior experience including staff qualifications | |
| Evaluation CriteriaProposed subcontractors | |
| Evaluation CriteriaProject Schedule | |
| Evaluation CriteriaLocal economic impact | |
| Mandatory CriteriaMandatory Criteria | Mandatory CriteriaReferees |
| Mandatory CriteriaFinancial Capacity | |
| Mandatory CriteriaAccredited WHS and Environmental Management Systems | |
| Mandatory CriteriaNominate and hold Key Personnel and Geosynthetic installer subcontractor | |
| Mandatory CriteriaGeosynthetic Installer pre-qualification |