Works on this upgrade will be completed in three stages.

Stage 1: Fowlers Road (South) – formerly known as Daisy Bank Drive

Works on Stage 1 of the Cleveland Road upgrade were completed in early 2026.

Road upgrades include:

  • 440 metres of road has been widened from two to four travel lanes and include kerb and gutter, stormwater drainage and street lighting.
  • The existing shared path on the eastern side of the road has been upgraded.

Stages 2 and 3: Cleveland Road

This stage covers approximately 2.5 km stretch of road west from Fowlers Road intersection. Road upgrades will include:

  • Stage 2 of Cleveland Road – 820m widened from two to four travel lanes
  • Stage 3 of Cleveland Road – 1780m widened to two travel lanes with kerbside parking on both sides
  • Road regrading (reshaping to make the road smoother and improve drainage), kerb and gutter, stormwater drainage, street lighting and a shared path on the northern side of Cleveland Road. A second shared path will be constructed on the southern side of the road after the services have been installed as part of the future subdivisions.
  • Intersection upgrade and installation of traffic lights at Fowlers Road and Cleveland Road

We'll be working closely with the community to manage the impacts of construction during all stages.

NSW Government logo

The Cleveland Road upgrade project is proudly co-funded by Restart NSW in association with Wollongong City Council.

aerial map showing stages of Cleveland Road upgrade