We’ve added a matrix for the Wollongong City Catchment into Chapter E13 of the Wollongong Development Control Plan PDF, 1824.81 KB. This helps people understand flood risks when they’re planning new development in the area.

Swan Street culvert  works

Culverts on Swan Street, Wollongong, near Kembla Street, have been upgraded to make them easier to maintain and reduce the chance of blockage.

Swan Street Swale Extension

The existing swale in JJ Kelly Park was extended by Council in 2018. This swale extension helps flood waters in Swan Street drain to JJ Kelly Park in very frequent events.

Vale Street and Gladstone Avenue stormwater inlet

We’ve made detailed designs to create an additional stormwater inlet at Vale Street and Gladstone Avenue, Mount Saint Thomas. This should reduce blockage and create better drainage. Construction is expected to start shortly.

Gurungaty Causeway

The lowering of the Gurungaty causeway is now complete. The works were completed in July 2019. Check out the Concept Design Report.

JJ Kelly Park

Investigations into work on JJ Kelly Park to improve the flow of water over the land are now complete. The feasibility study recommends no works be done in this location as the cost to do the works was significantly higher than the benefit the works would provide.

Allan Street Debris Control Structure

After intensive investigations into this option the project to design and construct a Debris Control Structure at the culvert inlet at 6 Allan Street was cancelled based on the lack of a feasible option for construction.